Atrium Finishes Move Forward

Installation of the unique Julius Bloom Glass hand rail system moved forward this week with the arrival of the tempered glass and stainless steel handrail and base trim. This hand rail system will allow an unimpeded view of our multi-story atrium.

Installation of the EAS System (electronic article surveillance) was completed and tested this week. This system is a technological method for preventing shoplifting.

Additional elevator installation personnel arrived this week as trim-out and final control wiring is completed. Store fixtures arrive daily. Crews worked in the store team management offices, as well as well as the sales floor areas. Electrical crews followed as fixtures are released for final wiring.

In the parking deck, stripping and parking signage installation nears completion.