Target Fixture Crews Onsite and Well Underway

Target fixture crews arrived on schedule and have moved forward with little break for the holidays. Work is well underway and electrical crews are coordinating with power and lighting installation as fixtures are made available.

Final equipment installation is ongoing at Food Avenue and Starbucks, with plumbing and electrical connection near completion. Elevator doors and frames have been installed, which has allowed final wall finishes to move forward.

Interior Target Signage installation is ongoing in the atrium as well as wayfinding signage in the parking deck. Ceiling grind installation is complete at the parking deck entrance to the atrium, and above ceiling work is ongoing. Our goal is for a ceiling cover-up in this area next week.