Store Fixturing Begins Monday

Sales floors have been cleared, swept and protected for the beginning of store fixturing, scheduled to begin on Monday, December 17th. Refrigerated case installation is now complete, and “soft” start-up will also begin on Monday.

Food Avenue casework and equipment installation nears completion. Starbucks is officially announced with signage installation. Elevator installation progressed this week, with the setting of doors and frames.

Atrium trim-out to escalators and Cartveyors is ongoing. Rear entrance storefront was completed. Remaining automatic doors will be installed the early part of next week. Parking deck specialized ceiling grid placement progressed as well.