Atrium and Parking Deck Entrances–High Priorities

Construction activities draw to a close at the upper level retail area as we prepare for store fixture activities to begin Dec. 17th. Installation of the food service equipment has started, while work at the atrium and parking deck continues.

Sheathing of atrium exterior ceiling moved forward this week after the installation of the redesigned parapet trim metal. Metal stair installation and concrete pours were completed this week as Cartveyors and Escalator installation was a prerequisite. Framing and sheetrock finishes to these structures is ongoing.